1420 NORTH ROAD over EAST MAIN CANAL
6.5 N 2.5 W RICHFIELD · County 063, Idaho · Built 2013 · 2 Lanes · 230 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
43.141111, -114.202778
This bridge is in worse condition than 11.3% of bridges in County 063. The average bridge in Idaho is 0 years old; this one is 13 years old.
Nearby Bridges
1150 EAST ROAD over EAST MAIN CANAL
Built 1977
850 EAST ROAD over EAST MAIN CANAL
Built 1965
1320 NORTH ROAD over EAST MAIN CANAL
Built 1950
1220 NORTH ROAD over EAST MAIN CANAL
Built 2024
1220 NORTH ROAD over STRATTON CANAL
Built 1968
1120 NORTH ROAD over STRATTON CANAL
Built 1950
820 NORTH ROAD over DIETRICH CANAL
Built 1994
1350 EAST ROAD over STRATTON CANAL
Built 2013
BURMAH ROAD over LINCOLN CANAL
Built 1974
920 NORTH ROAD over STRATTON CANAL
Built 2024
Bridge Details
- Structure #
- 000000000025101
- Year Built
- 2013
- Length
- 15.9 m (52.2 ft)
- Max Span
- 15.2 m
- Width
- 9.8 m (32.2 ft)
- Lanes
- 2
- Daily Traffic
- 230
- Material
- Prestressed Concrete
- Design
- Slab
- Owner
- Other Local Agencies
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- N/A
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.