DAMASCUS-HILTON RD over SOWHATCHEE CREEK

1.8 MILES SOUTHEAST OF HI · County 099, Georgia · Built 2021 · 2 Lanes · 480 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
000000009950700
Year Built
2021
Length
36.6 m (120.1 ft)
Max Span
18.3 m
Width
10.1 m (33.1 ft)
Lanes
2
Daily Traffic
480
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$10,656,000
Total Project Cost
$15,984,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.