LAKE CHAPEL CH RD over COLEMANS CREEK

12.9 MI SE OF SURRENCY · County 001, Georgia · Built 2022 · 2 Lanes · 1,153 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Bridge Details

Structure #
000000000150580
Year Built
2022
Length
64 m (210 ft)
Max Span
18.3 m
Width
9.1 m (29.9 ft)
Lanes
2
Daily Traffic
1,153
Material
Concrete
Design
Box Beam or Girders - Multiple
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$18,648,000
Total Project Cost
$27,972,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.