CR 269B-Juniper Rd over Yon Creek

1.5 Miles North of CR 269 · County 039, Florida · Built 2003 · 2 Lanes · 450 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

30.559728, -84.800739

This bridge is in worse condition than 28.9% of bridges in County 039. The average bridge in Florida is 0 years old; this one is 23 years old.

Nearby Bridges

Bridge Details

Structure #
504138
Year Built
2003
Length
31 m (101.7 ft)
Max Span
10.4 m
Width
13.1 m (43 ft)
Lanes
2
Daily Traffic
450
Material
Concrete Continuous
Design
Slab
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.