STATE ROUTE 29 SB over SUSCOL CREEK

04-NAP-029-R6.08 · County 055, California · Built 1981 · 2 Lanes · 32,500 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
7
Good

Bridge Details

Structure #
21 0071L
Year Built
1981
Length
18.9 m (62 ft)
Max Span
7.5 m
Width
17.1 m (56.1 ft)
Lanes
2
Daily Traffic
32,500
Material
Concrete Continuous
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$323,000
Total Project Cost
$542,000