I 19; SB over Anaconda Pipeline

0.6 mi N Jct Nogales Hwy · County 019, Arizona · Built 1971 · 2 Lanes · 21,137 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

31.913322, -110.986036

This bridge is in worse condition than 69.1% of bridges in County 019. The average bridge in Arizona is 0 years old; this one is 55 years old.

Nearby Bridges

Bridge Details

Structure #
01569
Year Built
1971
Length
20.7 m (67.9 ft)
Max Span
7.6 m
Width
13.6 m (44.6 ft)
Lanes
2
Daily Traffic
21,137
Material
Concrete Continuous
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0