I-22 over CR-30

CR-30 & I-22 · County 127, Alabama · Built 2004 · 2 Lanes · 13,401 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 7 Good

Location

33.9546, -87.6331

This bridge is in worse condition than 47.6% of bridges in County 127. The average bridge in Alabama is 0 years old; this one is 22 years old.

Nearby Bridges

Bridge Details

Structure #
017635
Year Built
2004
Length
105 m (344.5 ft)
Max Span
35 m
Width
12.8 m (42 ft)
Lanes
2
Daily Traffic
13,401
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$3,286,000
Total Project Cost
$3,615,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.