CO. RD. 54 over PERONE BRANCH
1.2 MI. W. CO. RD. 55 · County 003, Alabama · Built 1997 · 2 Lanes · 998 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
30.567269, -87.771167
This bridge is in worse condition than 65.2% of bridges in County 003. The average bridge in Alabama is 0 years old; this one is 29 years old.
Nearby Bridges
CO. RD. 54 over FISH RIVER
Built 1997
CO.RD.55 over PERONE CREEK
Built 1996
SR 104 over PERONE BRANCH
Built 1993
CR 55 over Branch off
Built 2024
SR 104 over FISH RIVER
Built 1993
CO. RD. 52 over SILVER CREEK
Built 1993
SR 104 over Silver Creek
Built 1993
CAMELLIA ROAD over DRAINAGE TO POLECAT CR.
Built 2005
US 90 over ROCK CREEK
Built 1929
CR 48 over Trib. to Polecat Cr _
Built 2017
Bridge Details
- Structure #
- 016842
- Year Built
- 1997
- Length
- 31.1 m (102 ft)
- Max Span
- 10.4 m
- Width
- 10.2 m (33.5 ft)
- Lanes
- 2
- Daily Traffic
- 998
- Material
- Concrete
- Design
- Channel Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $896,000
- Total Project Cost
- $986,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.