RAMP 54 over HOLT ST
I85 AND I65 INTERCHANGE · County 101, Alabama · Built 1973 · 2 Lanes · 9,497 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 7 | Good |
Location
32.366914, -86.320714
This bridge is in worse condition than 57.1% of bridges in County 101. The average bridge in Alabama is 0 years old; this one is 53 years old.
Nearby Bridges
RAMP 51 over HOLT ST.AND W.JEFF DAVIS
Built 1971
RAMP 59 over I65 AND RAMP 53
Built 1973
I-85 over W JEFF DAVIS * I-65
Built 1973
I65 SBL over RAMPS AND JEFF DAVIS AVE
Built 1973
I65 RAMP 52 over W.JEFF DAVIS AVE
Built 1972
I65 SBL/NBL over DAY ST
Built 1973
I85 over ROSA PARKS
Built 1971
FAP 94 (DAY ST) over OAK ST
Built 1973
FAP 94 (DAY ST) over OAK ST
Built 1973
I65 NBL / SBL over MILL ST
Built 1971
Bridge Details
- Structure #
- 010887
- Year Built
- 1973
- Length
- 68.6 m (225.1 ft)
- Max Span
- 24.4 m
- Width
- 12.8 m (42 ft)
- Lanes
- 2
- Daily Traffic
- 9,497
- Material
- Steel Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $2,274,000
- Total Project Cost
- $2,501,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.