CO RT 107 over PEA RIVER RELEIF

.9 MILES SE OF JAVA · County 031, Alabama · Built 1969 · 2 Lanes · 225 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 7 Good

Location

31.551317, -85.832214

This bridge is in worse condition than 69.4% of bridges in County 031. The average bridge in Alabama is 0 years old; this one is 57 years old.

Nearby Bridges

Bridge Details

Structure #
010029
Year Built
1969
Length
145.1 m (476 ft)
Max Span
10.4 m
Width
9 m (29.5 ft)
Lanes
2
Daily Traffic
225
Material
Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$3,041,000
Total Project Cost
$3,345,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.