CR-112 over Weogufka Creek

0.04 MI. E. CR-29 · County 037, Alabama · Built 1960 · 1 Lanes · 23 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
4
Poor
Substructure
6
Satisfactory

Bridge Details

Structure #
006847
Year Built
1960
Length
11.2 m (36.7 ft)
Max Span
11.2 m
Width
4.3 m (14.1 ft)
Lanes
1
Daily Traffic
23
Material
Wood or Timber
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$172,000
Total Project Cost
$189,000