WYO 59 over Spring Creek

Douglas - Reno Jct · County 005, Wyoming · Built 1979 · 2 Lanes · 2,898 vehicles/day

Overall
Fair
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 6 Satisfactory
Substructure 6 Satisfactory

Location

43.506978, -105.447494

This bridge is in worse condition than 44.7% of bridges in County 005. The average bridge in Wyoming is 0 years old; this one is 47 years old.

Nearby Bridges

Bridge Details

Structure #
DIR
Year Built
1979
Length
50.6 m (166 ft)
Max Span
19.2 m
Width
13 m (42.7 ft)
Lanes
2
Daily Traffic
2,898
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$10,000
Total Project Cost
$13,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.