LRD CLEOPHAS RD over RACCOON CREEK
0.7M E JCT CTH K · County 105, Wisconsin · Built 1918 · 2 Lanes · 82 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
3
Serious
Superstructure
3
Serious
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 3 | Serious |
| Superstructure | 3 | Serious |
| Substructure | 4 | Poor |
Location
42.55625, -89.213694
This bridge is in worse condition than 99% of bridges in County 105. The average bridge in Wisconsin is 0 years old; this one is 108 years old.
Nearby Bridges
LRD SKINNER RD over RACCOON CREEK
Built 2020
LRD BELOIT-NEWARK over RACCOON CREEK
Built 1996
LRD LARID ROAD over RACCOON CREEK
Built 1972
STH 81 over RACCOON CREEK
Built 1990
STH 81 over BR RACCOON CREEK
Built 1990
CTH H over BR COON CREEK
Built 2009
LRD BRANDHERM RD over BRA SUGAR RIVER
Built 1974
CTH H over RACCOON CREEK
Built 2005
LRD CLEOPHAS RD over E FK RACCOON CREEK
Built 2006
LRD BELOIT-NEWARK over E FK RACCOON CREEK
Built 2003
Bridge Details
- Structure #
- P53014600000000
- Year Built
- 1918
- Length
- 7.8 m (25.6 ft)
- Max Span
- 7.2 m
- Width
- 6.6 m (21.7 ft)
- Lanes
- 2
- Daily Traffic
- 82
- Material
- Concrete
- Design
- Slab
- Owner
- Town or Township Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $94,000
- Total Project Cost
- $142,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.