CTH M over MULLET RIVER

0.1M S JCT CTH PP · County 117, Wisconsin · Built 1954 · 2 Lanes · 180 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
5
Fair
Superstructure
4
Poor
Substructure
5
Fair

Bridge Details

Structure #
B59000200000000
Year Built
1954
Length
20.1 m (65.9 ft)
Max Span
9.6 m
Width
8.2 m (26.9 ft)
Lanes
2
Daily Traffic
180
Material
Prestressed Concrete
Design
Box Beam or Girders - Multiple
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$233,000
Total Project Cost
$349,000