CTH G over CHIPPEWA RIVER 29

2.4M W JCT CTH W · County 113, Wisconsin · Built 1980 · 2 Lanes · 235 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
4
Poor
Superstructure
8
Very Good
Substructure
6
Satisfactory

Bridge Details

Structure #
B57002600000000
Year Built
1980
Length
63.7 m (209 ft)
Max Span
21.1 m
Width
10.4 m (34.1 ft)
Lanes
2
Daily Traffic
235
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$645,000
Total Project Cost
$967,000