IH 94 EB over CARR CREEK

4.7M E JCT USH 63 TO N · County 109, Wisconsin · Built 2023 · 2 Lanes · 18,650 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
9
Excellent

Bridge Details

Structure #
B55028100000000
Year Built
2023
Length
37 m (121.4 ft)
Max Span
14.9 m
Width
19.2 m (63 ft)
Lanes
2
Daily Traffic
18,650
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.