LRD BIBON RD over WHITE RIVER
0.6M W JCT USH 63 · County 007, Wisconsin · Built 1984 · 2 Lanes · 76 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 4 | Poor |
Location
46.413769, -91.061131
This bridge is in worse condition than 94.2% of bridges in County 007. The average bridge in Wisconsin is 0 years old; this one is 42 years old.
Nearby Bridges
USH 63 over BIBON CREEK
Built 1990
USH 63 over WHITE RIVER
Built 1987
LRD MAPLE RIDGE RD over WHITE RIVER
Built 1990
LRD SWEDEN RD over TWENTY MILE CREEK
Built 1990
LRD TAYLOR LANE (D over LONG LAKE BRANCH
Built 2014
USH 63 over SCHRAMM CREEK
Built 1980
LRD OLD HWY 63 over EIGHTEEN MILE CREEK
Built 2019
LRD 4 CORNERS RD over MARENGO RIVER
Built 1981
LRD ALTAMONT RD over MARENGO RIVER
Built 1999
CTH E over BRANCH OF MARENGO RIVER
Built 2017
Bridge Details
- Structure #
- B04003600000000
- Year Built
- 1984
- Length
- 29 m (95.1 ft)
- Max Span
- 14.2 m
- Width
- 7.9 m (25.9 ft)
- Lanes
- 2
- Daily Traffic
- 76
- Material
- Concrete Continuous
- Design
- Slab
- Owner
- Town or Township Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $257,000
- Total Project Cost
- $386,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.