212TH WAY SE over GREEN RIVER
0.1 MI S OF GREEN VAL RD · County 033, Washington · Built 1991 · 2 Lanes · 3,862 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
47.282206, -122.0549
This bridge is in worse condition than 48.8% of bridges in County 033. The average bridge in Washington is 0 years old; this one is 35 years old.
Nearby Bridges
212TH WAY SE over NEWAUKUM CREEK
Built 2000
228 PLACE SE over GREEN RIVER
Built 1991
FLAMING GEYSER RD over BEAVER CREEK
Built 2017
SE GREEN VALLEY RD over BURNS CREEK
Built 1926
SE 400TH ST over NEWAUKUM CREEK
Built 1927
SR 169 over GREEN R
Built 1932
SE 416TH ST over NEWAUKUM CREEK
Built 1950
168TH WAY SE over COVINGTON CREEK
Built 1964
SR 164 over PUSSYFOOT CREEK
Built 2021
SR 169 over RAVENSDALE CREEK
Built 2022
Bridge Details
- Structure #
- 085983000000000
- Year Built
- 1991
- Length
- 78.3 m (256.9 ft)
- Max Span
- 51.8 m
- Width
- 12.4 m (40.7 ft)
- Lanes
- 2
- Daily Traffic
- 3,862
- Material
- Prestressed Concrete Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $4,820,000
- Total Project Cost
- $9,639,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.