RAMP F OF I-95NB over HUNTING CREEK & WETLANDS

00.50FR241/00.10TO0001 · County 059, Virginia · Built 2005 · 1 Lanes · 4,044 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Bridge Details

Structure #
000000000027081
Year Built
2005
Length
54.9 m (180.1 ft)
Max Span
18.3 m
Width
12.1 m (39.7 ft)
Lanes
1
Daily Traffic
4,044
Material
Prestressed Concrete Continuous
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$1,000,000
Total Project Cost
$2,500,000