ROUTE 23 SBL over NORFORK&SOUTHERN RAILWAY

2.10FRWISECL;2.30TOSCOTCL · County 105, Virginia · Built 1975 · 2 Lanes · 9,292 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
9
Excellent
Substructure
7
Good

Bridge Details

Structure #
000000000010696
Year Built
1975
Reconstructed
2024
Length
47.4 m (155.5 ft)
Max Span
17.5 m
Width
13.2 m (43.3 ft)
Lanes
2
Daily Traffic
9,292
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$75,000,000
Total Project Cost
$117,000,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.