Mossing Ford Road over Roanoke Creek

0.46 to 643 - 0.06 to 767 · County 037, Virginia · Built 1960 · 2 Lanes · 331 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
2
Critical

Bridge Details

Structure #
000000000004920
Year Built
1960
Length
48.2 m (158.1 ft)
Max Span
15.2 m
Width
8.3 m (27.2 ft)
Lanes
2
Daily Traffic
331
Material
Prestressed Concrete
Design
Slab
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$585,000,000
Total Project Cost
$877,000,000