BLUE MOUNTAIN ROAD over GREEN RIVER

APPROXIMATELY 13 MILES FR · County 047, Utah · Built 1966 · 2 Lanes · 300 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 6 Satisfactory

Location

40.408789, -109.234461

This bridge is in worse condition than 47.8% of bridges in County 047. The average bridge in Utah is 0 years old; this one is 60 years old.

Nearby Bridges

Bridge Details

Structure #
1400001P0000000
Year Built
1966
Length
123.1 m (403.9 ft)
Max Span
33.8 m
Width
9.8 m (32.2 ft)
Lanes
2
Daily Traffic
300
Material
Steel Continuous
Design
Stringer/Multi-beam or Girder
Owner
National Park Service
Last Inspected
N/A
Est. Improvement
$75,000
Total Project Cost
$113,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.