US 77 SB over FM 2826

US 77 AT FM 2826 · County 355, Texas · Built 2018 · 2 Lanes · 19,600 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
8
Very Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 8 Very Good
Substructure 8 Very Good

Location

27.739997, -97.699967

This bridge is in worse condition than 70.4% of bridges in County 355. The average bridge in Texas is 0 years old; this one is 8 years old.

Nearby Bridges

Bridge Details

Structure #
161780010202181
Year Built
2018
Length
77.7 m (254.9 ft)
Max Span
29 m
Width
12.2 m (40 ft)
Lanes
2
Daily Traffic
19,600
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.