FM 1354 over Dry Ecleto Creek

0.56 MI E OF SH 80 · County 255, Texas · Built 2021 · 2 Lanes · 252 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 8 Very Good
Substructure 7 Good

Location

29.004731, -97.812347

This bridge is in worse condition than 44.8% of bridges in County 255. The average bridge in Texas is 0 years old; this one is 5 years old.

Nearby Bridges

Bridge Details

Structure #
161290142201002
Year Built
2021
Length
36.6 m (120.1 ft)
Max Span
18.3 m
Width
11 m (36.1 ft)
Lanes
2
Daily Traffic
252
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0