GARRETT RD over CARPENTERS BAYOU
0.65 MI E OF BW 8 · County 201, Texas · Built 1977 · 2 Lanes · 5,925 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 6 | Satisfactory |
Location
29.883211, -95.186981
This bridge is in worse condition than 54.5% of bridges in County 201. The average bridge in Texas is 0 years old; this one is 49 years old.
Nearby Bridges
BW 8 E over GARRETT RD
Built 2011
LAKE HOUSTON PKWY over COH FRESHWATER CANAL
Built 1955
N LAKE HOU PKWY over E FORK SHELDON RESERVOIR
Built 1991
BW 8 E over LITTLE YORK RD
Built 2011
BW 8 E over C E KING PKWY
Built 2011
BW 8 E over LAKE HOUSTON PKWY
Built 2011
GARRETT RD over COH FRESHWATER CANAL
Built 1960
Park Road 138 over Canoe Trail
Built 2013
Park Road 138 over Fresh Water Canal
Built 2013
Van Hut Lane over HCFCD Ditch P121-00-00
Built 2022
Bridge Details
- Structure #
- 121020AA4468001
- Year Built
- 1977
- Length
- 61 m (200.1 ft)
- Max Span
- 15.2 m
- Width
- 9.4 m (30.8 ft)
- Lanes
- 2
- Daily Traffic
- 5,925
- Material
- Prestressed Concrete
- Design
- Box Beam or Girders - Multiple
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $10,000
- Total Project Cost
- $13,000