OPAL RD. over BEAVER DAM CK
9 S 8.5 E MAURINE · County 093, South Dakota · Built 1966 · 2 Lanes · 23 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
7
Good
Superstructure
6
Satisfactory
Substructure
4
Poor
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 6 | Satisfactory |
| Substructure | 4 | Poor |
Location
44.892528, -102.437797
This bridge is in worse condition than 88.7% of bridges in County 093. The average bridge in South Dakota is 0 years old; this one is 60 years old.
Nearby Bridges
FOX RIDGE RD. over BEAVER CK
Built 1978
FOX RIDGE RD. over CK
Built 1965
OPAL RD. over CK
Built 2022
OPAL RD. over HORSE CK
Built 1995
GRAPEVINE RD. over BEAVER CK
Built 2002
OPAL RD. over PINE CK
Built 1999
FOX RIDGE RD. over PINE CK
Built 1999
TRIPLE CREEK RD. over SULPHUR CK
Built 1940
FOX RIDGE RD. over SULPHUR CK
Built 1995
AVANCE RD. over CK
Built 1960
Bridge Details
- Structure #
- 000000047575100
- Year Built
- 1966
- Length
- 26.8 m (87.9 ft)
- Max Span
- 8.8 m
- Width
- 9.6 m (31.5 ft)
- Lanes
- 2
- Daily Traffic
- 23
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,000
- Total Project Cost
- $10,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.