HARDING GROVE ROAD over WEST PLUM CK
7.7E&3.5N MILESVILLE · County 055, South Dakota · Built 1988 · 2 Lanes · 28 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 6 | Satisfactory |
Location
44.507611, -101.522775
This bridge is in worse condition than 53.6% of bridges in County 055. The average bridge in South Dakota is 0 years old; this one is 38 years old.
Bridge Details
- Structure #
- 000000028237165
- Year Built
- 1988
- Length
- 19.8 m (65 ft)
- Max Span
- 19.5 m
- Width
- 7.1 m (23.3 ft)
- Lanes
- 2
- Daily Traffic
- 28
- Material
- Prestressed Concrete
- Design
- Tee Beam
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $5,000
- Total Project Cost
- $10,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.