212TH STREET over S. FORK OF PEARL CREEK
4S & 0.9W OF IROQUOIS · County 005, South Dakota · Built 1922 · 2 Lanes · 56 vehicles/day
Structurally Deficient
— One or more key components rated 4 (Poor) or below
Overall
Deck
5
Fair
Superstructure
5
Fair
Substructure
3
Serious
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 5 | Fair |
| Substructure | 3 | Serious |
Location
44.310728, -97.868142
This bridge is in worse condition than 91.3% of bridges in County 005. The average bridge in South Dakota is 0 years old; this one is 104 years old.
Nearby Bridges
211TH STREET over S. FORK OF PEARL CREEK
Built 2024
214TH STREET over S. FORK OF PEARL CREEK
Built 2018
215TH STREET over CREEK
Built 1932
212TH STREET over MIDDLE PEARL CREEK
Built 1928
208TH ST over SOUTH FORK PEARL CK
Built 1933
US014 over SOUTH FORK PEARL CK
Built 1965
413TH AVENUE over MIDDLE PEARL CREEK
Built 1930
US014 over MIDDLE PEARL CK
Built 1965
412TH AVENUE over MIDDLE PEARL CREEK
Built 1930
US014 over CK
Built 1965
Bridge Details
- Structure #
- 000000003411220
- Year Built
- 1922
- Length
- 9.1 m (29.9 ft)
- Max Span
- 8.8 m
- Width
- 5.5 m (18 ft)
- Lanes
- 2
- Daily Traffic
- 56
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $620,000
- Total Project Cost
- $797,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.