PR 18 NOBD 4.50 KM over PR 21 1.20 KM

5.8 KM N E OF GUAYNABO · County 127, Puerto Rico · Built 1965 · 4 Lanes · 119,500 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Bridge Details

Structure #
009582
Year Built
1965
Reconstructed
1978
Length
76.5 m (251 ft)
Max Span
26.8 m
Width
23.8 m (78.1 ft)
Lanes
4
Daily Traffic
119,500
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$2,549,000
Total Project Cost
$3,059,000