Three Mill Road over McMullin Creek

6.3 mi NE / Cave Junction · County 033, Oregon · Built 2002 · 1 Lanes · 30 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
3
Serious
Superstructure
5
Fair
Substructure
4
Poor

Bridge Details

Structure #
20990 000 00000
Year Built
2002
Length
20.1 m (65.9 ft)
Max Span
15.8 m
Width
4.1 m (13.5 ft)
Lanes
1
Daily Traffic
30
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
Other Local Agencies
Last Inspected
N/A
Est. Improvement
$215,000
Total Project Cost
$345,000