FREITAG RD over MILL CREEK

006 MI N CR653 · County 043, Oregon · Built 1959 · 2 Lanes · 21 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Poor
Deck
8
Very Good
Superstructure
6
Satisfactory
Substructure
4
Poor

Bridge Details

Structure #
12799 065400027
Year Built
1959
Length
17.7 m (58.1 ft)
Max Span
5.8 m
Width
7.8 m (25.6 ft)
Lanes
2
Daily Traffic
21
Material
Concrete
Design
Channel Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$242,000
Total Project Cost
$387,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.