TALLMAN ROAD over ALBANY-SANTIAM CANAL
001 MI S CR 9 · County 043, Oregon · Built 1962 · 2 Lanes · 433 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
44.576061, -122.967239
This bridge is in worse condition than 20.6% of bridges in County 043. The average bridge in Oregon is 0 years old; this one is 64 years old.
Nearby Bridges
LANGMACK RD over ALBANY-SANTIAM CANAL
Built 1962
KGAL DR over DITCH
Built 1970
RED BRIDGE RD over LITTLE OAK CREEK
Built 1959
GORE ROAD over LITTLE OAK CREEK
Built 1968
RED BRIDGE RD over ALBANY-SANTIAM CANAL
Built 1950
BOLHKEN DRIVE over BURKHART CREEK
Built 2009
GOLTRA RD over TRIB.LITTLE OAK CREEK
Built 2002
GOLTRA RD. over OAK CR TRIBUTARY
Built 2002
STECKLEY RD over OAK CREEK OVERFLOW
Built 1961
OR 34 (Hwy 210) over UPRR
Built 1990
Bridge Details
- Structure #
- 12682 066000089
- Year Built
- 1962
- Length
- 9.1 m (29.9 ft)
- Max Span
- 8.8 m
- Width
- 7.5 m (24.6 ft)
- Lanes
- 2
- Daily Traffic
- 433
- Material
- Prestressed Concrete
- Design
- Slab
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- N/A
- Total Project Cost
- $0
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.