29 S 03 W 33.00: over DAYS CREEK
7.6 miles NE of Hwy 227 ( · County 019, Oregon · Built 1971 · 1 Lanes · 20 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
43.023611, -123.045281
This bridge is in worse condition than 39.4% of bridges in County 019. The average bridge in Oregon is 0 years old; this one is 55 years old.
Nearby Bridges
29 S 03 W 15.01: over SOUTH MYRTLE CREEK
Built 1970
29 S 03 W 16.00: over Weaver Creek
Built 2004
29 S 03 W 11.00: over SOUTH MYRTLE CREEK
Built 1970
COUNTY RD 18 over SOUTH MYRTLE CREEK
Built 1961
COUNTY RD 18 over SOUTH MYRTLE CREEK
Built 2024
COUNTY RD 18 over SOUTH MYRTLE CREEK
Built 1961
DAYS CR RD over DAYS CREEK
Built 1956
COUNTY RD 18 over SOUTH MYRTLE CREEK
Built 1961
DAYS CR RD over DAYS CREEK
Built 1956
COUNTY RD 18 over SOUTH MYRTLE CREEK
Built 1961
Bridge Details
- Structure #
- 0000000L1439308
- Year Built
- 1971
- Length
- 33.5 m (109.9 ft)
- Max Span
- 21.3 m
- Width
- 5 m (16.4 ft)
- Lanes
- 1
- Daily Traffic
- 20
- Material
- Concrete Continuous
- Design
- Stringer/Multi-beam or Girder
- Owner
- Bureau of Land Management
- Last Inspected
- N/A
- Est. Improvement
- $1,000
- Total Project Cost
- $1,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.