IRR BIA RTE 2 over SHITIKE CREEK

AT JCT BIA 2002 AND BIA 2 · County 031, Oregon · Built 1998 · 2 Lanes · 50 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 8 Very Good

Location

44.748967, -121.638264

This bridge is in worse condition than 21.3% of bridges in County 031. The average bridge in Oregon is 0 years old; this one is 28 years old.

Nearby Bridges

Bridge Details

Structure #
00000000000P946
Year Built
1998
Length
21.8 m (71.5 ft)
Max Span
21 m
Width
8.5 m (27.9 ft)
Lanes
2
Daily Traffic
50
Material
Prestressed Concrete
Design
Slab
Owner
Bureau of Indian Affairs
Last Inspected
N/A
Est. Improvement
$0
Total Project Cost
$0