E0970 over CREEK
4.6W 2N OF ARAPAHO · County 039, Oklahoma · Built 2009 · 2 Lanes · 25 vehicles/day
Overall
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 7 | Good |
| Substructure | 7 | Good |
Location
35.609594, -99.074139
This bridge is in worse condition than 21.4% of bridges in County 039. The average bridge in Oklahoma is 0 years old; this one is 17 years old.
Nearby Bridges
E0970 over WEST BARNITZ CREEK
Built 2008
E0970 over EAST BARNITZ CREEK
Built 1990
N2200 over WEST BARNITZ CREEK
Built 1996
E0980 over WEST BARNITZ CREEK
Built 1990
E0980 over EAST BARNITZ CREEK
Built 1988
S.H. 33 over EAST BARNITZ CREEK OFLO
Built 2023
2046C over CREEK
Built 1982
S.H. 33 over EAST BARNITZ CREEK
Built 2023
S.H. 33 over WEST BARNITZ CREEK OFLO
Built 2024
S.H. 33 over WEST BARNITZ CREEK
Built 2023
Bridge Details
- Structure #
- 293050000000000
- Year Built
- 2009
- Length
- 6.7 m (22 ft)
- Max Span
- 6.6 m
- Width
- 7.7 m (25.3 ft)
- Lanes
- 2
- Daily Traffic
- 25
- Material
- Steel
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $80,000
- Total Project Cost
- $225,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.