7504 C over SPRING CREEK

4.0 N 1.0 E. COLONY · County 149, Oklahoma · Built 2006 · 2 Lanes · 50 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 8 Very Good

Location

35.406386, -98.658853

This bridge is in worse condition than 21.9% of bridges in County 149. The average bridge in Oklahoma is 0 years old; this one is 20 years old.

Nearby Bridges

Bridge Details

Structure #
283990000000000
Year Built
2006
Length
7.3 m (24 ft)
Max Span
7 m
Width
8.2 m (26.9 ft)
Lanes
2
Daily Traffic
50
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$84,000
Total Project Cost
$225,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.