E1270 over CREEK

4.2E 2.5S OF ERICK · County 009, Oklahoma · Built 2003 · 2 Lanes · 25 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
8
Very Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 8 Very Good
Substructure 7 Good

Location

35.174928, -99.792733

This bridge is in worse condition than 34.2% of bridges in County 009. The average bridge in Oklahoma is 0 years old; this one is 23 years old.

Nearby Bridges

Bridge Details

Structure #
275320000000000
Year Built
2003
Length
9.1 m (29.9 ft)
Max Span
8.8 m
Width
8.2 m (26.9 ft)
Lanes
2
Daily Traffic
25
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$161,000
Total Project Cost
$257,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.