N2430 over DEER CREEK

N OF WEATHERFORD;3E OK 54 · County 039, Oklahoma · Built 2004 · 2 Lanes · 100 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

35.577758, -98.667706

This bridge is in worse condition than 21.4% of bridges in County 039. The average bridge in Oklahoma is 0 years old; this one is 22 years old.

Nearby Bridges

Bridge Details

Structure #
272220000000000
Year Built
2004
Length
67.7 m (222.1 ft)
Max Span
29.9 m
Width
8.7 m (28.5 ft)
Lanes
2
Daily Traffic
100
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$1,231,000
Total Project Cost
$1,956,000