U.S. 54 EB over PONY CREEK

10.8NE OF SH-3 JCT. · County 139, Oklahoma · Built 2000 · 2 Lanes · 3,400 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
7
Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 7 Good
Substructure 8 Very Good

Location

36.777264, -101.33075

This bridge is in worse condition than 63.2% of bridges in County 139. The average bridge in Oklahoma is 0 years old; this one is 26 years old.

Nearby Bridges

Bridge Details

Structure #
266000000000000
Year Built
2000
Length
41.8 m (137.1 ft)
Max Span
13.7 m
Width
12.2 m (40 ft)
Lanes
2
Daily Traffic
3,400
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$944,000
Total Project Cost
$2,644,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.