IRR E1470 over MISSION CREEK
1. S 5.4 W OF SH 19 · County 015, Oklahoma · Built 1999 · 2 Lanes · 100 vehicles/day
Overall
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 7 | Good |
| Superstructure | 8 | Very Good |
| Substructure | 7 | Good |
Location
34.884075, -98.451814
This bridge is in worse condition than 26.5% of bridges in County 015. The average bridge in Oklahoma is 0 years old; this one is 27 years old.
Nearby Bridges
N2550 over CREEK
Built 1940
N2550 over CREEK
Built 1940
IRR 0866C over CREEK
Built 2001
IRR N2540 over TAHOE CREEK
Built 1993
IRR N2540 over TAHOE CREEK
Built 1993
N2560 over CREEK
Built 1976
IRR FAS 0868C over CREEK
Built 2003
S.H. 19 over CREEK
Built 1936
N2560 over TAHOE CREEK
Built 1982
E1480 over CREEK
Built 2001
Bridge Details
- Structure #
- 261940000000000
- Year Built
- 1999
- Length
- 22.4 m (73.5 ft)
- Max Span
- 21.3 m
- Width
- 8.3 m (27.2 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $269,000
- Total Project Cost
- $429,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.