6242C over CREEK

4.5S & 6.7W OF FITTSTOWN · County 123, Oklahoma · Built 1992 · 2 Lanes · 100 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
8
Very Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 8 Very Good

Location

34.549367, -96.751897

This bridge is in worse condition than 34.9% of bridges in County 123. The average bridge in Oklahoma is 0 years old; this one is 34 years old.

Nearby Bridges

Bridge Details

Structure #
230100000000000
Year Built
1992
Length
22.1 m (72.5 ft)
Max Span
21.3 m
Width
10.5 m (34.4 ft)
Lanes
2
Daily Traffic
100
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$267,000
Total Project Cost
$426,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.