N4170 over BLUE CREEK

1.8 S 1 W OF HAILEYVIL · County 121, Oklahoma · Built 1991 · 2 Lanes · 50 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
8
Very Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 8 Very Good
Substructure 7 Good

Location

34.828928, -95.601817

This bridge is in worse condition than 41.1% of bridges in County 121. The average bridge in Oklahoma is 0 years old; this one is 35 years old.

Nearby Bridges

Bridge Details

Structure #
228260000000000
Year Built
1991
Length
31.1 m (102 ft)
Max Span
30.5 m
Width
8.5 m (27.9 ft)
Lanes
2
Daily Traffic
50
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$322,000
Total Project Cost
$514,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.