E1930 over CREEK

1 N & 1.2 E OF EMET · County 069, Oklahoma · Built 1985 · 2 Lanes · 24 vehicles/day

Overall
Fair
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 6 Satisfactory
Superstructure 6 Satisfactory
Substructure 6 Satisfactory

Location

34.216075, -96.520856

This bridge is in worse condition than 51.9% of bridges in County 069. The average bridge in Oklahoma is 0 years old; this one is 41 years old.

Nearby Bridges

Bridge Details

Structure #
209700000000000
Year Built
1985
Length
13.9 m (45.6 ft)
Max Span
13.7 m
Width
6.4 m (21 ft)
Lanes
2
Daily Traffic
24
Material
Prestressed Concrete
Design
Tee Beam
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$208,000
Total Project Cost
$331,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.