S.H. 3 over LEADER CREEK

7.6 MI E PONTOTOC C/L · County 029, Oklahoma · Built 1977 · 2 Lanes · 2,600 vehicles/day

Overall
Fair
Deck
8
Very Good
Superstructure
7
Good
Substructure
6
Satisfactory

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 7 Good
Substructure 6 Satisfactory

Location

34.602647, -96.396336

This bridge is in worse condition than 53.1% of bridges in County 029. The average bridge in Oklahoma is 0 years old; this one is 49 years old.

Nearby Bridges

Bridge Details

Structure #
193470000000000
Year Built
1977
Length
61.9 m (203.1 ft)
Max Span
20.4 m
Width
15.1 m (49.5 ft)
Lanes
2
Daily Traffic
2,600
Material
Prestressed Concrete
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$736,000
Total Project Cost
$2,060,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.