U.S. 64 EB over GENERAL OFLOW
20.93 E JCT US-59 · County 135, Oklahoma · Built 1975 · 2 Lanes · 10,500 vehicles/day
Overall
Deck
5
Fair
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 5 | Fair |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
35.395225, -94.437342
This bridge is in worse condition than 75.2% of bridges in County 135. The average bridge in Oklahoma is 0 years old; this one is 51 years old.
Nearby Bridges
U.S. 64 EB over GENERAL OFLOW
Built 1975
U.S. 64 over ARK RIVER & R.R./ CO.RD.
Built 1973
U.S. 64 WB over GENERAL OFLOW
Built 1975
U.S. 64 over OLD OK-64 UNDER
Built 1958
U.S. 64 over OLD OK-64 UNDER
Built 1975
U.S. 64 over GENERAL OFLOW
Built 1975
US 64 - District 4 over ARK RVR & ARKMO/BN RRS
Built 1973
U.S. 64 EB over GARRISON TRIB OFLOW
Built 1975
U.S. 64 WB over GENERAL OFLOW
Built 1956
S.H. 64D over U.S. 64 UNDER
Built 1976
Bridge Details
- Structure #
- 191070000000000
- Year Built
- 1975
- Length
- 207.9 m (682.1 ft)
- Max Span
- 12.2 m
- Width
- 13.3 m (43.6 ft)
- Lanes
- 2
- Daily Traffic
- 10,500
- Material
- Prestressed Concrete
- Design
- Stringer/Multi-beam or Girder
- Owner
- State Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $1,502,000
- Total Project Cost
- $4,204,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.