S.H. 59 over PANTHER CREEK

6.8 MI S. JCT. SH 39 · County 087, Oklahoma · Built 1959 · 2 Lanes · 850 vehicles/day

Overall
Good
Deck
8
Very Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 8 Very Good
Superstructure 7 Good
Substructure 7 Good

Location

34.917381, -97.564825

This bridge is in worse condition than 35.1% of bridges in County 087. The average bridge in Oklahoma is 0 years old; this one is 67 years old.

Nearby Bridges

Bridge Details

Structure #
143890000000000
Year Built
1959
Reconstructed
2016
Length
36.9 m (121.1 ft)
Max Span
12.2 m
Width
9.8 m (32.2 ft)
Lanes
2
Daily Traffic
850
Material
Steel
Design
Stringer/Multi-beam or Girder
Owner
State Highway Agency
Last Inspected
N/A
Est. Improvement
$581,000
Total Project Cost
$1,627,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.