E0070 over CREEK

.1W 3.6N 5.4W OF GATE · County 007, Oklahoma · Built 1939 · 2 Lanes · 100 vehicles/day

Overall
Good
Deck
7
Good
Superstructure
7
Good
Substructure
7
Good

Condition Ratings

ComponentRatingDescription
Deck 7 Good
Superstructure 7 Good
Substructure 7 Good

Location

36.906306, -100.156953

This bridge is in worse condition than 35.4% of bridges in County 007. The average bridge in Oklahoma is 0 years old; this one is 87 years old.

Nearby Bridges

Bridge Details

Structure #
071490000000000
Year Built
1939
Length
12.2 m (40 ft)
Max Span
2.4 m
Width
7.9 m (25.9 ft)
Lanes
2
Daily Traffic
100
Material
Concrete
Design
Slab
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$196,000
Total Project Cost
$311,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.