E0200 over CREEK

1S&1.7W JCTUS60&SH125 · County 115, Oklahoma · Built 1939 · 2 Lanes · 100 vehicles/day

Structurally Deficient — One or more key components rated 4 (Poor) or below
Overall
Serious
Deck
4
Poor
Superstructure
4
Poor
Substructure
2
Critical

Condition Ratings

ComponentRatingDescription
Deck 4 Poor
Superstructure 4 Poor
Substructure 2 Critical

Location

36.728492, -94.8858

This bridge is in worse condition than 98.5% of bridges in County 115. The average bridge in Oklahoma is 0 years old; this one is 87 years old.

Nearby Bridges

Bridge Details

Structure #
070890000000000
Year Built
1939
Length
9 m (29.5 ft)
Max Span
3.7 m
Width
6.1 m (20 ft)
Lanes
2
Daily Traffic
100
Material
Concrete Continuous
Design
Slab
Owner
County Highway Agency
Last Inspected
N/A
Est. Improvement
$168,000
Total Project Cost
$265,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.