8.0 S 6.1 W GOTEBO · County 075, Oklahoma · Built 1930 · 2 Lanes · 100 vehicles/day
Overall
Deck
6
Satisfactory
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 6 | Satisfactory |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
34.957289, -98.978253
This bridge is in worse condition than 68.6% of bridges in County 075. The average bridge in Oklahoma is 0 years old; this one is 96 years old.
Nearby Bridges
N2250 over CREEK
Built 2016
N2260 over CREEK
Built 1941
N2260 over RAINY MOUNTAIN CREEK
Built 1941
E1400 over CREEK
Built 1930
N2260 over CREEK
Built 1930
N2270 over RAINY MOUNTAIN CREEK
Built 2007
N2260 over CREEK
Built 1930
N2230 over CREEK
Built 1994
N2270 over CREEK
Built 2023
N2280 over CREEK
Built 2010
Bridge Details
- Structure #
- 024990000000000
- Year Built
- 1930
- Length
- 7.3 m (24 ft)
- Max Span
- 3 m
- Width
- 8 m (26.2 ft)
- Lanes
- 2
- Daily Traffic
- 100
- Material
- Concrete Continuous
- Design
- Slab
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $149,000
- Total Project Cost
- $236,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.