COUNTY HIGHWAY 83 over CREEK
6 EAST OF JUDSON · County 059, North Dakota · Built 1948 · 2 Lanes · 40 vehicles/day
Overall
Deck
8
Very Good
Superstructure
6
Satisfactory
Substructure
6
Satisfactory
Condition Ratings
| Component | Rating | Description |
|---|---|---|
| Deck | 8 | Very Good |
| Superstructure | 6 | Satisfactory |
| Substructure | 6 | Satisfactory |
Location
46.826344, -101.154872
This bridge is in worse condition than 50.2% of bridges in County 059. The average bridge in North Dakota is 0 years old; this one is 78 years old.
Nearby Bridges
COUNTY HIGHWAY 83 over SWEET BRIAR CREEK
Built 1981
COUNTY HIGHWAY 83 over CREEK
Built 1979
CR139 over CREEK
Built 1960
COUNTY HIGHWAY 139 over CREEK
Built 1930
COUNTY HIGHWAY over I-94/SWEET BRIAR INT
Built 1964
INTERSTATE 94 over CREEK
Built 1964
COUNTY ROAD 139A over CREEK
Built 1940
37TH STREET over CREEK
Built 1936
COUNTY HIGHWAY 83 over HEART RIVER
Built 1945
Lyons Road over SWEET BRIAR CREEK
Built 2003
Bridge Details
- Structure #
- 000000030145110
- Year Built
- 1948
- Length
- 9.8 m (32.2 ft)
- Max Span
- 9.1 m
- Width
- 7.4 m (24.3 ft)
- Lanes
- 2
- Daily Traffic
- 40
- Material
- Wood or Timber
- Design
- Stringer/Multi-beam or Girder
- Owner
- County Highway Agency
- Last Inspected
- N/A
- Est. Improvement
- $135,000
- Total Project Cost
- $203,000
Data from FHWA National Bridge Inventory. Bridge conditions may have changed since the last inspection. This site is not affiliated with FHWA. Do not use for route clearance purposes.